[README](/README.md#documentation) > **Functionality**
|
||||
|
||||
# Functionality
|
||||
|
||||
- N - Column Major Matrix
|
||||
- T - Row Major matrix
|
||||
- {N,T} x {N,T} - All combinations, i.e. NN, NT, TN, TT
|
||||
@ -18,8 +20,6 @@
|
||||
- SpTensorOp - Use Sparse Tensor Core MMA
|
||||
- WmmaTensorOp - Use WMMA abstraction to use Tensor Core MMA
|
||||
|
||||
# Functionality
|
||||
|
||||
## Device-level GEMM
|
||||
|
||||
The following table summarizes device-level GEMM kernels in CUTLASS, organized by opcode class, data type, and layout.
|
||||
|
||||
388
media/docs/grouped_scheduler.md
Normal file
388
media/docs/grouped_scheduler.md
Normal file
@ -0,0 +1,388 @@
|
||||

|
||||
|
||||
[README](/README.md#documentation) > **Grouped Kernel Schedulers**
|
||||
|
||||
# CUTLASS Grouped Kernel Schedulers
|
||||
|
||||
CUTLASS's grouped kernel is a persistent kernel which launches multiple problems (e.g., GEMMs, SYR2Ks) within a
|
||||
single CUDA kernel launch.
|
||||
|
||||
Unlike a conventional GEMMs in CUTLASS, which launch a number of threadblocks equal to the number
|
||||
of tiles in the GEMM, CUTLASS grouped kernels typically launch a number of threadblocks that is
|
||||
fewer than the total number of tiles across all problems in the group. Each threadblock is then
|
||||
responsible for computing one or more tiles among the problems in the group. The grouped kernel
|
||||
_scheduler_ (referred to as the _problem visitor_ in code) is responsible for assigning each
|
||||
threadblock the sequence of tiles that it will compute within the group.
|
||||
|
||||
This document provides background on the functionality of the grouped kernel scheduler, and describes
|
||||
various optimizations to the grouped kernel scheduler.
|
||||
|
||||
**Outline**
|
||||
|
||||
* [Introduction to Grouped Kernel Schedulers](grouped_scheduler.md#introduction-to-grouped-kernel-schedulers)
|
||||
* [Grouped GEMM Scheduler](grouped_scheduler.md#grouped-gemm-scheduler)
|
||||
* [Grouped Rank2K Scheduler](grouped_scheduler.md#grouped-rank2k-scheduler)
|
||||
* [Scheduler Modes](grouped_scheduler.md#scheduler-modes)
|
||||
* [Improving Load Balance by Sorting Problems](grouped_scheduler.md#improving-load-balance-by-sorting-problems)
|
||||
|
||||
# Introduction to Grouped Kernel Schedulers
|
||||
Given a group of problem sizes and a grid of threadblocks, the scheduler's job is to assign
|
||||
tiles from problems in the group to threadblocks. Threadblocks in a grouped kernel persistently
|
||||
execute a loop of querying the scheduler for the next tile to compute and performing the
|
||||
kernel-level operations for that tile (e.g., MMA and epilogue). In pseudocode, this looks as
|
||||
follows:
|
||||
```c++
|
||||
ProblemVisitor problem_visitor;
|
||||
|
||||
while (problem_visitor.next_tile()) {
|
||||
//
|
||||
// Get next tile index from scheduler
|
||||
//
|
||||
|
||||
//
|
||||
// Compute MMA and epilogue
|
||||
//
|
||||
|
||||
// Inform the scheduler that we are done with the current tile
|
||||
problem_visitor.advance(gridDim.x);
|
||||
}
|
||||
```
|
||||
|
||||
The key functionality of the grouped kernel scheduler lies in the `next_tile()` method,
|
||||
which determines which tile in the group the calling threadblock should compute next, if any.
|
||||
|
||||
# Grouped GEMM Scheduler
|
||||
The scheduler used by grouped GEMM assigns tiles in the group to threadblocks in a round-robin
|
||||
fashion.
|
||||
|
||||
Consider, for example, the threadblock-to-tile mapping that occurs for a group of four GEMMs
|
||||
each consisting of a grid of 2x2 tiles. Suppose that eight threadblocks are launched. The
|
||||
figure below illustrates the threadblock ID assigned to each tile in each GEMM in the group.
|
||||
|
||||

|
||||
|
||||
A similar mapping for problems that do not have the same number of tiles
|
||||
is shown below:
|
||||
|
||||

|
||||
|
||||
## Computing the schedule for a given block
|
||||
Each threadblock in the grouped GEMM computes its own schedule by calling
|
||||
the `next_tile()` method described above.
|
||||
|
||||
To do this, the threadblock's `ProblemVisitor` maintains a `thread_idx`
|
||||
member that is initialized to `blockIdx.x` and is incremented by
|
||||
`gridDim.x` between each tile computed (only the x dimension is used)
|
||||
in the launch configuration for grouped kernels). The scheduler must
|
||||
then figure out which GEMM in the group `tile_idx` belongs to, and which tile
|
||||
within that problem it maps to.
|
||||
|
||||
1. **Determining which GEMM `tile_idx` maps to:** The scheduler determines
|
||||
the GEMM to which `tile_idx` belongs by iterating through GEMMs starting with
|
||||
the most-recently visited GEMM, and adding the number of tiles within that
|
||||
GEMM to a running variable `problem_tile_start`. The scheduler has found the
|
||||
correct problem for this tile when `problem_tile_start <= tile_idx < problem_tile_start + tiles_in_problem`.
|
||||
|
||||
2. **Determining the tile within a GEMM `tile_idx` maps to:** Once the GEMM
|
||||
to which `tile_idx` maps has been located, the specific tile within that
|
||||
GEMM that this block should compute is given by `tile_idx - problem_tile_start`.
|
||||
Simple rasterization is then performed to map this one-dimensional tile ID
|
||||
into the two-dimensional coordinate of the tile to compute in the GEMM.
|
||||
|
||||
We describe how this search is accelerated in [Scheduler Modes](grouped_scheduler.md#scheduler-modes).
|
||||
|
||||
# Grouped Rank2K Scheduler
|
||||
The previous section described the operation of the scheduler used
|
||||
for grouped GEMM kernels. While this scheduler is sufficient for
|
||||
correctly implementing grouped Rank2K operations (i.e., SYR2K and HER2K), it leads to significant inefficiencies.
|
||||
|
||||
We next describe these inefficiencies as well as how the CUTLASS
|
||||
grouped Rank2K scheduler overcomes them.
|
||||
|
||||
## Inefficiency of grouped GEMM scheduler for grouped Rank2K problems
|
||||
The grouped GEMM scheduler assumes that every tile in every GEMM in the group will
|
||||
ultimately affect the output of the problem. This is not the case for Rank2K
|
||||
problems, for which matrix C is either upper or lower triangular. Using the default
|
||||
grouped GEMM scheduler for such problems will thus lead to threadblocks frequently
|
||||
being assigned to tiles that exit early (e.g., due to being assigned to a tile in the
|
||||
upper-triangular portion of a lower-triangular problem). This further leads to load
|
||||
imbalance among threadblocks, as the grouped GEMM scheduler assigns nearly the same
|
||||
number of tiles to all threadblocks, regardless of how many tiles are truly active.
|
||||
|
||||
Consider an example of a group of four SYR2K problems, each with matrix C consisting
|
||||
of a grid of 2x2 tiles. Matrix C in each problem is lower triangular, indicated by
|
||||
shaded tiles. Consider that eight threadblocks are launched to compute the grouped
|
||||
problem. The default grouped GEMM scheduler will assign threadblocks to tiles in the following order:
|
||||
|
||||

|
||||
|
||||
In this case, threadblocks 1 and 5 are continuously assigned to inactive tiles. In
|
||||
scenarios in which problems within the group have varying size, we have observed
|
||||
this to still lead to significant load imbalance.
|
||||
|
||||
## Specializing the scheduler for triangular problems
|
||||
We seek to design a scheduler that more efficiently maps threadblocks to active tiles
|
||||
for kernels that use triangular output matrices. The scheduler should ideally assign
|
||||
threadblocks only to those tiles within lower-triangular portion of a
|
||||
lower-triangular problem (and vice-versa for upper-triangular problems).
|
||||
|
||||
Using the example above, the resulting assignment of threadblocks to tiles from
|
||||
such a scheduler might be:
|
||||
|
||||

|
||||
|
||||
Achieving this schedule requires mapping from a threadblock ID to tile coordinates
|
||||
`(i, j)`.
|
||||
|
||||
We will illustrate this by mapping a lower-triangular matrix with a 3x3 grid. We
|
||||
first calculate row and column indices assuming one-indexed rows, tiles, and
|
||||
threadblock IDs, and then subtract one to convert to zero-indexed versions. Our
|
||||
description borrows heavily from the mapping described [here](https://stackoverflow.com/a/40954159).
|
||||
|
||||

|
||||
|
||||
### Calculating row `i` given threadblock ID `t`
|
||||
For a given row i, all threadblock IDs t in that row satisfy the following:
|
||||
```
|
||||
t <= 1 + 2 + 3 + ... + (i-1) + i
|
||||
```
|
||||
|
||||
The closed-form equation for the right-hand side is: `i(i+1)/2`.
|
||||
Using this, we can solve for `i` given `t`:
|
||||
```
|
||||
t <= i(i+1)/2
|
||||
2t <= i^2 + i
|
||||
2t <= i^2 + i + 0.25 - 0.25
|
||||
2t + 0.25 <= i^2 + i + 0.25
|
||||
2t + 0.25 <= (i + 0.5)^2
|
||||
sqrt(2t + 0.25) - 0.5 <= i
|
||||
```
|
||||
|
||||
To account for fractional values, we set:
|
||||
```
|
||||
i = ceil(sqrt(2t + 0.25) - 0.5)
|
||||
```
|
||||
|
||||
To turn this into a zero-indexed row and work with zero-indexed `t`, we perform:
|
||||
```
|
||||
i = ceil(sqrt(2(t+1) + 0.25) - 0.5) - 1
|
||||
= ceil(sqrt(2t + 2.25) - 0.5) - 1
|
||||
```
|
||||
|
||||
### Calculating column `j` given threadblock ID `t` and row `i`
|
||||
For a given row `i`, all threadblock IDs `t` in that row also satisfy the following:
|
||||
```
|
||||
t > 1 + 2 + 3 + ... + (i-2) + (i-1)
|
||||
--> t > i(i-1)/2
|
||||
```
|
||||
|
||||
Threadblock IDs within a given row are sequential, so the one-indexed column ID
|
||||
for one-indexed threadblock ID `t` and row `i` is:
|
||||
```
|
||||
j = t - (i(i-1)/2)
|
||||
```
|
||||
|
||||
The zero-indexed version becomes:
|
||||
```
|
||||
j = (t+1) - (i(i+1)/2) -1
|
||||
= t - (i(i+1)/2)
|
||||
```
|
||||
|
||||
### Accounting for non-square grids
|
||||
Though the overall output problem size for Rank2K problems is guaranteed to be square, the
|
||||
grids used in computing may not be square due to using non-square threadblock shapes. For
|
||||
example, a threadblock shape of 64x32 operating on a problem of output size 128x128 would
|
||||
result in a grid of 2x4 tiles.
|
||||
|
||||
This case can be handled by noting that the output resembles a square grid of 2x2 "macro tiles"
|
||||
each of which contains 2 "true tiles." We can thus first map a threadblock ID to its "macro tile"
|
||||
using the equations above, and then map it to the "true tile" within its "macro tile." In the example
|
||||
of a 2x4 grid, this mapping would look as follows:
|
||||
|
||||

|
||||
|
||||
A zero-indexed threadblock ID `t` is mapped to its "macro tile ID" `t_macro` as:
|
||||
```
|
||||
t_macro = t // r
|
||||
```
|
||||
Where `r` is the ratio of the maximum dimension of the grid to the
|
||||
minimum dimension of the grid (i.e., `r = 4 / 2 = 2` in the previous example).
|
||||
|
||||
One uses `t_macro` and the calculations above to find the row and column in the square matrix to
|
||||
obtain `i_macro` and `j_macro` (zero-indexed). The mapping from `(i_macro, j_macro) --> (i, j)`
|
||||
is simply the following:
|
||||
```
|
||||
if (ThreadblockShape::M > ThreadblockShape::N):
|
||||
r = ThreadblockShape::M / ThreadblockShape::N
|
||||
i = i_macro
|
||||
j = (j_macro * r) + (t % r)
|
||||
elif (ThreadblockShape::M < ThreadblockShape::N):
|
||||
r = ThreadblockShape::N / ThreadblockShape::M
|
||||
i = (i_macro * r) + (t % r)
|
||||
j = j_macro
|
||||
else:
|
||||
i = i_macro
|
||||
j = j_macro
|
||||
```
|
||||
|
||||
### Handling cases with grid dimensions that aren't multiples of each other
|
||||
Even though threadblock shapes M and N are typically multiples of one another, the grid
|
||||
for a given problem may not have dimensions of the same ratio as that of the threadblock.
|
||||
For example, a problem of size 132x132 using a threadblock of shape 64x32 will result
|
||||
in a grid of 3x5 tiles. In this case, there is not an integer number of "true tiles"
|
||||
per "macro tile."
|
||||
|
||||
When this scenario arises, we simply pad the larger dimension of the grid such that
|
||||
there are an integer number of "true tiles" per "macro tile." Thus, the 3x5 grid in
|
||||
the example above will be treated as a 3x6 grid. Row and column positions for each
|
||||
tile are calculated as above. Any threadblocks that map to tiles that are outside the
|
||||
problem range or upper/lower triangular portion (e.g., (2, 5)) will exit early from
|
||||
this problem and may proceed to the next problem in the group.
|
||||
|
||||
### Handling upper-triangular matrices
|
||||
The only modification needed for upper-triangular matrices is to swap `i_macro` and `j_macro` in the calculations above.
|
||||
|
||||
# Scheduler modes
|
||||
The grouped kernel schedulers come with two different modes for finding
|
||||
the next tile for a block to compute. These techniques are controlled by
|
||||
the [`cutlass::gemm::kernel::GroupScheduleMode`](../../include/cutlass/gemm/kernel/grouped_problem_visitor.h) enum.
|
||||
We describe each mode in greater detail below.
|
||||
|
||||
## `GroupScheduleMode::kDeviceOnly` (default)
|
||||
This scheduler mode performs all scheduling work on the device. It parallelizes
|
||||
the search for the problem that `tile_idx` maps to by having each thread "own"
|
||||
a different problem and determine whether `tile_idx` falls within the range of
|
||||
that problem.
|
||||
|
||||
`GroupScheduleMode::kDeviceOnly` performs this parallelization in a warp-wide
|
||||
fashion. Each thread in the warp loads a problem size indexed by its lane id and
|
||||
computes the number of tiles in that problem. A warp-wide prefix sum is used to find
|
||||
the starting tiles for the set of problems the warp is looking at. At the end of the
|
||||
prefix sum, each thread holds the starting tile index and tile count for a unique
|
||||
problem in the group.
|
||||
|
||||
While `tile_idx` remains within the range of the problems currently hosted by the
|
||||
warp, each thread will check whether `tile_idx` is in the range of its current
|
||||
problem. The matching problem index and its starting tile are then broadcasted to all
|
||||
threads in the warp.
|
||||
|
||||
## Precomputing schedules on the host: `GroupScheduleMode::kHostPrecompute`
|
||||
This scheduler attempts to reduce the amount of scheduling performed on the device
|
||||
by precomputing on the host the sequence of problems that will
|
||||
be accessed by each block. As described above, all that is needed to map tile_idx to
|
||||
the specific tile within a problem to compute is the problem ID and the problem's
|
||||
starting tile (among all of the tiles in the group). Thus, this scheduler precomputes
|
||||
the problem index and problem starting tile for each tile computed by each block.
|
||||
|
||||
The schedule for an individual block is represented as an array of
|
||||
`(problem_idx, problem_starting_tile)` tuples. There is one such array per block.
|
||||
These arrays are produced on the host and copied over to the device. This
|
||||
representation is optimized for the case in which blocks compute at most one
|
||||
tile per problem. When a block computes multiple tiles per problem in the group,
|
||||
the representation above will result in duplicate entries, and thus will be
|
||||
suboptimal (e.g., `[(3, 20), (3, 20)]` for a block that computes two tiles in
|
||||
problem 3, which has starting tile index 20).
|
||||
We have chosen to use the representation described above because grouped kernels
|
||||
themselves are typically most beneficial when problem sizes are small, and, thus,
|
||||
blocks compute at most one tile per problem.
|
||||
|
||||
## Which scheduler mode should I use?
|
||||
Consider the following questions when deciding which scheduling mode to use:
|
||||
|
||||
### How are the parameters used as input to the grouped kernel (e.g., ptrA, lda) set in my application?
|
||||
If these are set by a previous kernel running on
|
||||
the device (rather than by the host), you likely want to use `kDeviceOnly`,
|
||||
as this will minimize additional host-device communication.
|
||||
|
||||
### Can host-side work be overlapped with other device kernels in my application?
|
||||
For example, if a grouped GEMM is used as the Nth layer in a neural network,
|
||||
host-side precomputation for the grouped GEMM can potentially be overlapped
|
||||
with device-side work for layer N-1. In this case `kHostPrecompute` is likely
|
||||
a good fit.
|
||||
|
||||
### How compute-intensive are the problems in my group?
|
||||
The differences in performance between `kHostPrecompute` and `kDeviceOnly` are most
|
||||
noticeable for grouped kernels with low computational intensity, for which time spent in
|
||||
the scheduler accounts for a significant fraction of the grouped kernel's runtime.
|
||||
Intuitively, as problems in a group decrease in computational intensity, a smaller
|
||||
fraction of the overall runtime will be consumed in performing MMA operations, leading
|
||||
to a larger fraction of the overall runtime being consumed by scheduling logic.
|
||||
|
||||
Since the scheduling modes affect only the scheduling logic of the grouped kernels,
|
||||
one expects to see most benefit from `kHostPrecompute` for less computationally-intense
|
||||
groups.
|
||||
|
||||
# Improving Load Balance by Sorting Problems
|
||||
The grouped kernel schedulers assign a nearly equal number
|
||||
of tiles to each block participating in the grouped kernel. Every tile in the
|
||||
group has the same M and N dimensions. However, the K dimension of each
|
||||
tile depends on the K dimension of the problem, so tiles may have different
|
||||
K dimensions. Thus, the K dimension of the
|
||||
tile plays a significant role in determining how long it takes for a given
|
||||
tile to be computed.
|
||||
|
||||
## Potential problems with imbalanced K dimension
|
||||
To ensure that compute load is balanced evenly across blocks, it is important
|
||||
that the sum of the K dimensions among all tiles a block computes be similar
|
||||
to that of other blocks; if one block computes far more tiles with a large
|
||||
value of K than other blocks, it may take longer than the other blocks.
|
||||
|
||||
For example, consider the following group of GEMMs:
|
||||
```
|
||||
0 1152x768x128
|
||||
1 1152x768x1024
|
||||
2 768x1152x128
|
||||
3 768x1152x1024
|
||||
```
|
||||
If a tile size of 128x128 is used, then each problem will have 54 tiles.
|
||||
Thus, there are 216 tiles across the group.
|
||||
|
||||
Suppose this grouped GEMM is run on GA100, which has 108 SMs. Suppose that
|
||||
the occupancy given the parameters of the grouped GEMM is one -- one threadblock
|
||||
can be active at a time on an SM. The grouped GEMM will, thus, run with 108
|
||||
persistent threadblocks, each of which computes (256 / 108) = 2 tiles.
|
||||
|
||||
Under the round-robin assignment of tiles to threadblocks employed by
|
||||
the grouped GEMM scheduler, the assignment of tiles to threadblocks
|
||||
in this GEMM will be as follows:
|
||||
```
|
||||
Threadblocks 0-53: Tiles of size 128x128x128 from problem 0
|
||||
Threadblocks 54-107: Tiles of size 128x128x1024 from problem 1
|
||||
Threadblocks 0-53: Tiles of size 128x128x128 from problem 2
|
||||
Threadblocks 54-107: Tiles of size 128x128x1024 from problem 3
|
||||
```
|
||||
|
||||
Following this assignment, threadblocks 54-107 perform significantly more
|
||||
work than threadblocks 0-53 because they compute two tiles with a K
|
||||
dimension of 1024, whereas threadblocks 0-53 compute two tiles with K
|
||||
dimension of only 128.
|
||||
|
||||
Due to this imbalanced assignment, threadblocks 54-107 will run
|
||||
significantly longer than threadblocks 0-53, leaving threadblocks
|
||||
0-53 idle for a large fraction of time.
|
||||
|
||||
Clearly, a better assignment of tiles to threadblocks for this
|
||||
example would involve all threadblocks computing one tile with
|
||||
a K dimension of 1024 and one tile with a K dimension of 128.
|
||||
This would better balance the workload among threadblocks.
|
||||
|
||||
## Potential for sorting problems to reduce imbalance
|
||||
A simple way to potentially reduce load imbalance is to sort the problems in a group in
|
||||
descending order of their K dimension. This can help to improve load balance
|
||||
because tiles in a group are assigned in a round-robin fashion to blocks
|
||||
sequentially, so every block will always be assigned next the tile with
|
||||
the highest K dimension available.
|
||||
|
||||
Considering the example described above, sorting the problem sizes before
|
||||
executing grouped GEMM improves the runtime of this grouped GEMM on GA100 with each
|
||||
scheduling mode by around 30%.
|
||||
|
||||
To ease the process of sorting groups and their associated metadata in this
|
||||
manner, the device-level grouped kernels provide a `sort_problems()` method.
|
||||
An example of how to use this may be found in the [grouped GEMM example](../../examples/24_gemm_grouped/gemm_grouped.cu).
|
||||
|
||||
Finally, while sorting problems can be helpful in certain scenarios, it is
|
||||
not guaranteed to improve performance. In some cases, performance can
|
||||
decrease when sorting problems due to additional conflicting factors that
|
||||
affect GEMM performance. We recommend profiling your grouped kernel with
|
||||
and without sorting to see whether it helps in your case.
|
||||
BIN
media/images/grouped-gemm-schedule-2x2.png
Executable file
BIN
media/images/grouped-gemm-schedule-2x2.png
Executable file
Binary file not shown.
|
After Width: | Height: | Size: 6.1 KiB |
BIN
media/images/grouped-gemm-schedule-varied.png
Executable file
BIN
media/images/grouped-gemm-schedule-varied.png
Executable file
Binary file not shown.
|
After Width: | Height: | Size: 5.8 KiB |
BIN
media/images/grouped-syr2k-schedule-3x3.png
Executable file
BIN
media/images/grouped-syr2k-schedule-3x3.png
Executable file
Binary file not shown.
|
After Width: | Height: | Size: 4.4 KiB |
BIN
media/images/grouped-syr2k-schedule-ideal.png
Executable file
BIN
media/images/grouped-syr2k-schedule-ideal.png
Executable file
Binary file not shown.
|
After Width: | Height: | Size: 6.5 KiB |
BIN
media/images/grouped-syr2k-schedule-macro.png
Executable file
BIN
media/images/grouped-syr2k-schedule-macro.png
Executable file
Binary file not shown.
|
After Width: | Height: | Size: 8.2 KiB |
BIN
media/images/grouped-syr2k-schedule-using-grouped-gemm-scheduler.png
Executable file
BIN
media/images/grouped-syr2k-schedule-using-grouped-gemm-scheduler.png
Executable file
Binary file not shown.
|
After Width: | Height: | Size: 6.9 KiB |
Reference in New Issue
Block a user